Dismantling and Assembly Work at ZGH
We recently carried out dismantling and assembly work at a Mining and Metallurgical Plant (ZGH) near Olkusz. The project required the use of modern equipment and precise team coordination to ensure efficient and safe operations.
Project Details
To complete the project, we used:
- Liebherr LTM 1650-8.1, serving as the main crane responsible for high-altitude work.
The work involved dismantling a 125-meter chimney and installing a new, lower chimney. The task was particularly challenging due to the height and the precision required during the placement of the new structure.
The entire operation lasted 2 weeks and was completed according to schedule without any issues.
Team and Equipment Support
Our technical department oversaw all key stages of the project, while our transport department was responsible for logistics and the efficient organization of equipment on the job site.
Efficiency and Precision
By utilizing the Liebherr LTM 1650-8.1 crane and our team’s expertise, the task was carried out in accordance with the highest safety and quality standards. The project provided yet another confirmation of our readiness to take on complex assignments in demanding conditions.