Relocation of a Tower Crane in Poznań
Recently, we had the pleasure of carrying out the relocation of a tower crane at a construction site in Poznań for one of our long-standing partners. The project required precise organization and the use of modern equipment to ensure the safety and efficiency of the entire process.
Project Details
We used the following equipment for the task:
- Liebherr LTM 1350-6.1, with a lifting capacity of 350 tons, serving as the main crane for assembly and disassembly work.
Selecting the right driving specifications for the mobile cranes allowed for smooth transit to the worksite, adhering to permissible values and standards.
The task took 3 days and included:
- Setting up the LTM 1350-6.1 crane on the construction site – this required precise site preparation and equipment configuration.
- Disassembling and reassembling the tower crane, carried out according to technical guidelines.
- Stability and functionality tests, ensuring the safety and effectiveness of the operation.
Team and Equipment Support
Our experienced technical crew was also involved in the project, supervising each stage of the task to maintain the schedule and the highest safety standards.
Efficiency and Precision
Thanks to the use of the modern Liebherr LTM 1350-6.1 crane and our team’s expertise, the task was completed without any setbacks. This project once again confirmed our reliability and commitment to carrying out even the most demanding assignments.